Kothapalli-Manoharabad railway line to be completed by 2027: Bandi Sanjay
The Hindu
Efforts underway to complete Kothapalli-Manoharabad railway line by 2027, with 76.135 km already constructed, costing ₹2,780.78 crore.
The Kothapalli-Manoharabad railway line has been a long-cherished dream of people of the erstwhile composite Karimnagar and Medak districts and efforts are on to complete its construction and make it operational by 2027, said Union Minister of State for Home Affairs Bandi Sanjay Kumar in Karimnagar on Friday.
Addressing the media after reviewing the progress of various railway projects in Karimnagar Parliamentary constituency in Karimnagar on Friday, the Union Minister said renewed focus has been laid on the speedy completion of the long pending railway line. The Central government approved the 151.36 km Kothapalli-Manoharabad new railway line in July 2016, with an estimated cost of ₹1,160.48 crore. But significant delays occurred due to land acquisition issues. For the railway line to be completed, the revised estimate indicates a total expenditure of ₹2,780.78 crore. So far, ₹1,444.17 crore has been spent, he said, adding that the State government is required to contribute one-third of the total project cost as per the agreement.
Out of the total 151.36 km of the project, construction work for 76.135 km has been completed so far. Over 75 km of work still remains, he said.
In the 2024-25 budget, ₹350 crore has been sanctioned, of which ₹262.93 crore has already been spent. The target is to complete over 30 km of railway line construction in the Siddipet and Rajanna Sircilla districts by September this year, he noted.
Stating that the State government is responsible for acquiring the land for the construction of the railway line as per the agreement, he said significant delays in land acquisition hindered the progress of construction. Currently, 90% of the land acquisition issues have been resolved. Out of the total 2,830 acres of land required, 199 acres remain to be acquired.
The construction work for 31.06 km from Vemulawada to Kothapalli and for 10.7 km in Rajanna Sircilla district is expected to be completed by March, 2026.
He further added that plans are afoot to develop Kothapalli railway station into a junction station with freight handling facilities.
The Criminal Investigation Department (CID), probing the death of contractor, Sachin Panchal, who allegedly ended his life in Bidar on December 26 last year, arrested five persons, including the prime accused Rajkumar Kapnoor, a former member of the Kalaburagi Mahanagara Palike, and reportedly a follower of Rural Development and Panchayat Raj Minister, Priyank Kharge, on Friday.