Sanikiluaq wind project represents major Nunavut renewable energy policy shift
CBC
A lone windmill in Sanikiluaq, Nunavut, which is expected to produce enough power to cut the community's reliance on diesel fuel by half, is all but a done deal.
On Sept. 29, the Qulliq Energy Corporation (QEC) and the Nunavut Nukkiksautiit Corporation (NNC) are expected to sign an agreement for the power corporation to buy the electricity generated from the windmill.
The signing is significant because it's the first time the QEC will agree to buy electricity from an independent provider. But it also represents a major policy shift in Nunavut, paving the way for other renewable energy projects to be built and have their electricity sold to the territorial power corporation.
As CBC reported in November 2022, disagreements between NNC and QEC stalled the Sanikiluaq wind project — formally known as the Anuriqjuak Nukkiksautiit Project — because QEC never had a policy in place for how to purchase electricity from independent producers. The Sanikiluaq project has been in the works since 2016.
NNC director Heather Shilton said at the time QEC wouldn't engage with her group because it lacked such a policy.
In a recent interview with CBC News, Shilton wouldn't elaborate on the details of the agreement for the Sanikiluaq project until it's signed next week. But she said QEC received ministerial approval in the fall of 2022 to accept applications under its independent power producers program.
"We applied under the program and we've been talking to them since that time about the project in Sanikiluaq," Shilton said.
"We've been chatting with them for the last 10 to 12 months I would say, now that they have the approval to accept applications."
QEC refused CBC's request for an interview on the new policy direction because it wanted to issue a press release first.
Nunavut Premier P.J. Akeeagok, who is the minister responsible for QEC, also refused to comment on the ministerial decision behind QEC's new policy until the signing ceremony in Sanikiluaq.
In its filing to the Nunavut Impact Review Board in 2021, NNC stressed the project (if successful) could be a catalyst for other communities in the territory.
"The project will demonstrate how community-scale renewable energy projects can be safely integrated with the local electrical grid. It will enhance the grid by providing a back-up source of energy when the diesel generators need to be offline," NNC wrote in its filing.
"Nunavut needs to transition from diesel to sustainable energy systems. Renewable energy generation not only makes environmental sense, but also provides economic opportunities for Inuit."
The windmill is expected to produce one megawatt of power, with a one megawatt hour storage battery for the community of 1,000 people.