K-100 project: Sewage flow still a challenge
The Hindu
BWSSB officials claim nearly 98% of sewage flow has been checked so far
The work on developing K-100, considered to be one of the most historically significant raja kaluves (major storm-water drains) in the city, is progressing well and around 65% of the work has been completed, claimed Bruhat Bengaluru Mahanagara Palike (BBMP) officials.
The major challenge, however, continues to be preventing the flow of sewage into the drain, said civic officials, adding that if it had been plugged completely, more progress could have been achieved.
The project, which began in March 2021, was to be completed in 10 months.
A senior official told The Hindu that the waterfront beautification work near the Bengaluru Metropolitan Transport Corporation’s (BMTC) bus terminus at Shanthinagar had been completed. The major drain connected the erstwhile Dharmabudhi lake, where the Kempegowda Bus Station now stands, with Bellandur lake.
“Work on nearly 5 km of the drain has been completed. There is some progress in the work taken up on the remaining stretches,” the official said and added that the entire drain length of around 10 km had been divided into different worksites, each measuring 1 km.
However, Bangalore Water Supply and Sewerage Board (BWSSB) has countered the BBMP’s claim on sewage flow in the drain. A senior BWSSB official, who spoke to The Hindu on condition of anonymity, said that 95-98% of sewage flow into the drain had been checked. “Earlier, nearly 120 mld (million litres per day) of sewage would flow into the drain. We have managed to bring it down to less than 5 mld now,” the official said.
The official, however, said that there may be some unauthorised connections letting out sewage into the secondary drains connected to the raja kaluve.
The girl, who was admitted to Aster CMI Hospital with alarming breathlessness and significant pallor, was diagnosed with Wegener’s Granulomatosis (now known as Granulomatosis with Polyangiitis or GPA), a rare autoimmune condition that causes spontaneous bleeding in the lungs, leading to acute respiratory failure.
ACB files case against IPS officer N. Sanjay in Andhra Pradesh. The official is accused of manipulating the tender processes for awarding contract for development and maintenance of AGNI-NOC portal, and conducting awareness meetings for SC/STs. It is alleged that the total value of properties stolen, or involved in the case is estimated at ₹1,75,86,600.