Jagan sets deadline for Polavaram canal works
The Hindu
CM inspects project progress, tells officials to focus on R&R package
Chief Minister Y.S. Jagan Mohan Reddy has set a target of completing the works related to lining and linking of the two major channels of the Indira Sagar Multi-Purpose Project (Polavaram) by June 2022 and completion of tunnel works by December 2022. Mr. Jagan Mohan Reddy along with Ministers, MLAs and senior irrigation officials reviewed the progress of the project on Monday. Mr. Jagan Mohan Reddy, who reached the Polavaram dam site in a chopper, inspected the project from the view point and later inspected the progress of works from the spill way.More Related News