Eglinton Crosstown plagued by 260 quality control issues, including improperly laid track: Metrolinx CEO
CBC
The repeatedly delayed and over-budget Eglinton Crosstown LRT is being held up by some 260 quality control issues and there is still no credible timeline for its completion, the head of Ontario's provincial transit agency said Thursday.
At an unrelated transit announcement in Toronto, Metrolinx CEO Phil Verster offered up his most detailed public explanation to date of the myriad problems plaguing the 25-stop, 19-km mega project. The light rail line was slated to finally open last fall after nearly 12 years of construction and multiple earlier delays.
"My biggest concern is that the quality is right and we get a safe transit system. We are building infrastructure here for the next 100, 150 years, and we've got to get it right," Verster said alongside Minister of Transportation Caroline Mulroney.
The pair laid much of the blame for the delays at the feet of Crosslinx Transit Solutions (CTS), a consortium of four companies contracted by Ontario's previous Liberal government to design and build the Crosstown.
Perhaps the single-biggest issue among a litany of problems, Verster said, is that track laid in 2021 was built outside of Metrolinx's specifications and the mistake is only now being fixed by CTS. A misstep of just a few millimetres runs the risk of a train climbing onto the tracks and derailing, Verster said.
"This is not centimetres of error, this is millimetres of error. Anyone who builds track should know that. It is unfortunate this didn't get done right," he told reporters.
"Despite our urging and our guidance, it is only being rectified now and it will have a two month impact, at least, on the completion of the project."
Verster added that CTS's initial designs for the Crosstown — which will likely cost roughly $13 billion before it is finished — were nine months, or in some cases up to 18 months, late. That has translated into major delays in the testing and commissioning phase of the project, which is only about 50 per cent completed at this point, Verster said.
"We have pushed CTS to rethink their schedule and restructure their resources and the work that is being done on testing and commissioning," he added. "We cannot start with the training of the TTC operators until the system is fully completed and ready."
Similarly, CTS's own engineers must certify each part of the work is up to Metrolinx's stated quality standards — a process that is only 20 per cent complete, Verster said.
Verster said that CTS is bearing the costs of the necessary fixes and delays and that Metrolinx is using "every lever and every remedy" available in the contract to push the consortium to finally deliver the Crosstown. That includes withholding "substantial payments against completion of the project," he said.
Pressed on a potential timeline for its opening, Mulroney said that CTS has failed to offer a "credible" schedule.
CBC Toronto has reached out to CTS for comment. This story will be updated with CTS's response if one is provided.
The Ministry of Transportation and Metrolinx have faced backlash over what critics have called a disturbing lack of transparency around the Crosstown construction process. Several Toronto city councillors who represent wards affected by the work have called for a public inquiry into the delays.
A disgraced real-estate lawyer who this week admitted to pilfering millions in client money to support her and her family's lavish lifestyle was handcuffed in a Toronto courtroom Friday afternoon and marched out by a constable to serve a 20-day sentence for contempt of court, as her husband and mother watched.
Quebec mayor says 'one-size-fits-all' language law isn't right for his town where French is thriving
English is not Daniel Côté's first language but he says it's integral to the town he calls home.