TransitNext submits ‘substantial completion notice’ for Trillium Line
CTV
The consortium responsible for building Ottawa's new north-south line, TransitNext, says it is ready for the City of Ottawa to begin the final phase of approvals before opening the line to the public.
The consortium responsible for building Ottawa's new north-south line, TransitNext, says it is ready for the City of Ottawa to begin the final phase of approvals before opening the line to the public.
A memo sent on Wednesday afternoon from OC Transpo's general manager Renee Amilcar says TransitNext submitted its "substantial completion" notice to the city last week.
The city and an independent certifier are now reviewing documentation and contract requirements needed to make sure the project can move into the "final readiness" stage, Amilcar said.
"As part of this process, the City is currently assessing TransitNext’s notice of substantial completion and will provide an opinion to the Independent Certifier and TransitNext," Amilcar wrote.
"The Independent Certifier will then review the TransitNext’s Notice of Substantial Completion and the City’s opinion to confirm that all requirements have been met. Once this determination is made, the Independent Certifier will issue the Substantial Completion Certificate."
Substantial completion is the final step before the system is handed over to the City of Ottawa. This includes the completion of all infrastructure construction, regulatory approvals, safety and security certifications.
Once TransitNext hands the keys of the line to the city, the project will move into the final readiness stage, where the city will have to complete several more certification requirements and approvals before launching.