Toronto is on the hook for millions to replace failing water meters
CBC
Work to replace parts of 470,000 failing water meters in homes and businesses across Toronto is underway, but the latest update shows it will cost taxpayers millions of dollars to solve the problem that's only getting worse.
In July, civil servants said thousands of radio transmitters on water meters were failing years ahead of schedule, meaning they can't relay usage from homes or businesses to the city. In a new report to councillors on the infrastructure committee, Toronto Water says over 150,000 of those units have now failed and the city will need to spend $5.6 million on the first wave of replacements.
But getting new units has been complicated by supply chain problems and the fact that the technology is now obsolete. The general manager of Toronto Water, Lou Di Gironimo, said that means city residents are increasingly being billed by estimates based on their historic usage.
"It is a growing problem," he said. "We started to notice a significant number of the meter transmission units failing. The meters are fine, so they are registering properly. It is just about sending us the data on a wireless basis."
But that has meant some customers are receiving unexpectedly large bills because their actual water usage isn't being relayed in real time. Toronto Water receives 92 per cent of its funding from water sales, which are measured by 470,000 meters on homes and businesses.
"We want to restore customer service back to what (residents) were used to," Di Gironimo said. "Most importantly, it is our cash register. That's how we calculate our revenues accurately."
The culprit is small lithium batteries in the transmission units. Once projected to have a 20-year lifespan, they are now failing at the 11 or 12 year mark, the city says. In 2010, the city began a five-year replacement program of its old water meters to the new digital versions.
Installation of those new units started to peak in 2011 and 2012 and those are the units failing now.
The city estimated a unit failure rate of one per cent, or about 4,700, a year prior to this issue. But Di Gironimo said they're now failing at a rate of 5,000 to 8,000 units a month.
That means the batteries in every transmission unit in the city will be dead between three to five years. And it will take years to replace the units, he said.
"We ask residents to be patient with us, because this is going to take us several years to deal with. This is not a quick fix," he said.
When the city initially went public about the problem in July, it said the meters were under warranty. But the latest report says the city negotiated a sole-sourced emergency contract with the company that makes the units, Aclara Technologies, to acquire a supply of "initial" replacement units for $5.6 million. Those units were under warranty that covered some, but not all of the costs.
Staff are now asking city councillors for permission to continue negotiations with Aclara for a supply of additional equipment. Details about those talks are part of a confidential report to councillors.
The cost to replace every unit in the city isn't yet clear because of the talks.
Burlington MP Karina Gould gets boost from local young people after entering Liberal leadership race
A day after entering the Liberal leadership race, Burlington, Ont., MP and government House leader Karina Gould was cheered at a campaign launch party by local residents — including young people expressing hope the 37-year-old politician will represent their voices.
Two years after Foreign Affairs Minister Mélanie Joly declared she was taking the unprecedented step of moving to confiscate millions of dollars from a sanctioned Russian oligarch with assets in Canada, the government has not actually begun the court process to forfeit the money, let alone to hand it over to Ukrainian reconstruction — and it may never happen.