Ottawa quietly announces cost of building new supply ships has jumped by almost $1 billion
CBC
The cost to build the navy's often-delayed, long-anticipated supply ships has shot up once again — this time by almost $1 billion — the federal procurement department announced Friday.
Successive federal governments have tried for almost two decades to deliver joint support ships (JSS) to the navy — vessels used to replenish warships at sea.
After years of delay, the Liberal government awarded Seaspan's Vancouver Shipyards Co. Ltd. a build contract in June 2020 for two ships — HMCS Protecteur and HMCS Preserver — at an anticipated cost of $2.44 billion.
Public Services and Procurement Canada (PSPC) chose to announce in a media statement on Friday — the eve of the August long weekend — a major amendment to the contract which drives up the price tag to $3.3 billion.
And that figure does not include the design cost, in-service support and other expenses related to the program. When those numbers are added, the total bill for taxpayers for owning and operating the ships is now expected to exceed $5.2 billion.
"This increased contract value was calculated by considering a number of factors, such as lessons learned from developing a new type of warship for the [Royal Canadian Navy], COVID-19 impacts that resulted in labour and supply chain disruptions, economic price adjustments, foreign exchange rate fluctuations, and changes in labour rates," said the statement.
PSPC did not rule out further cost increases, saying the federal "continues to actively monitor progress on the JSS project and is working with [Vancouver Shipyards] to ensure timely delivery of both vessels to the RCN."
The new ships are meant to replace the navy's long-retired original replenishment vessels, which were taken out of service a decade ago or more after 30 years at sea.
Ottawa began the process of acquiring new ships two decades ago. The first program was scrapped by Prime Minister Stephen Harper's government in 2008 — by press release on a Friday night in the middle of August, on the eve of the federal election that year.
The program was restarted, but not before the old supply ships had to be retired.
The navy couldn't do without a replenishment capability, so the Harper government turned to a private company — based out of the Dave Shipyard in Levis, Que. — to convert a civilian ship, the MV Asterix, which remains in service under a long-term lease.
Canada's parliamentary budget office did an analysis in late 2020 that said converting two civilian cargo ships to serve as resupply vessels for the navy would have been cheaper than continuing with the joint support program.
When the build contract with Seaspan was signed, the first ship was slated for delivery in 2023 and the second in 2025.
But federal officials warned in the spring of 2023 that those delivery dates had to be pushed two years into the future. They also said that costs likely would rise, but they couldn't say by how much.
Burlington MP Karina Gould gets boost from local young people after entering Liberal leadership race
A day after entering the Liberal leadership race, Burlington, Ont., MP and government House leader Karina Gould was cheered at a campaign launch party by local residents — including young people expressing hope the 37-year-old politician will represent their voices.
Two years after Foreign Affairs Minister Mélanie Joly declared she was taking the unprecedented step of moving to confiscate millions of dollars from a sanctioned Russian oligarch with assets in Canada, the government has not actually begun the court process to forfeit the money, let alone to hand it over to Ukrainian reconstruction — and it may never happen.