N.W.T. pitches smaller, more realistic $328M capital budget
CBC
The N.W.T. can't spend money fast enough on existing capital projects, so it's revising how it's budgeting them and in some cases pushing timelines back on when they will be completed.
A proposed $328-million 2023-24 capital budget was tabled in the legislature Tuesday.
The territory's capital budgets have steadily climbed in recent years, but this one reverses course and is more than a third smaller than the previous year's budget of $502 million.
There are no new big-ticket items proposed and no changes to annual allocations for small capital projects like annual highway chipseal work.
Instead, the proposed budget takes into account what the government and industry in the territory is actually capable of delivering, said Finance Minister Caroline Wawzonek.
"It's still large, but it is one that is more realistic so that when you get excited about it, there's more transparency as to what we actually have on the list," she said during a media briefing alongside her colleagues from the finance department before the budget's tabling.
They described what they say is a new approach to developing the capital budget.
It involved asking departments to review previously approved projects and provide updated cost estimates and timelines.
In some cases, the completion dates for projects like the Fort Providence Transmission Line, which would connect the community to the Taltson hydroelectric transmission system, have been pushed back.
The transmission line was originally expected to be finished by 2022-23. Now, it's expected to be connected by 2024-25.
An environmental assessment for the Slave Geological Province All Weather Highway, originally scheduled to be done by 2023-24, is now expected to be done by 2027-28.
In other cases, some projects that were expected to have been completed by now — like long-term care facilities in Hay River and Inuvik — have revised end dates.
The long-term care facility in Hay River is expected to be done by now 2027-28, while the facility in Inuvik has been moved back to the planning stage.
"The projects aren't disappearing," Wawzonek said. "The fact of the matter, though, is if you leave it on the capital list and you say 'here, it's here,' that doesn't get it any closer to completion."