'Milestone' hit as wind turbine arrives in Inuvik; but project now more than $20M over budget
CBC
It wasn't easy delivering a single 3.5-megawatt wind turbine — with blades that at 67 metres span more than the width of a football field — but with the help of three barges, the parts began to arrive in Inuvik, N.W.T. on Tuesday.
And, it was done without damage, says the Northwest Territories government, calling it a "milestone" feat. Albeit. the project, and the shipping itself, was delayed due to various reasons.
"It's not like we're driving a transport truck down the major highway," said Steve Hagerman director of Marine Transport in Hay River.
Hagerman said "considerable groundwork" was done at the terminal in Inuvik last month to make sure it was level, among other "enhancements" to prepare for the barges.
The turbine is part of the Inuvik Wind Project, which officials hope will reduce the amount of diesel needed for power in the community by 30 per cent. That would offset diesel consumption in Inuvik, the N.W.T.'s largest diesel-powered community, by three million litres annually, the territory said.
Tony Coleman, who's into his 12th season of being a deckhand, said he's never witnessed such a large delivery.
"This is the biggest I've ever seen," he said. "We've had big fuel tanks and everything we've taken to DEW line sites, but I've never seen anything like this take up the full length of the barge [and] it's sticking out over too."
Construction of the project began in January 2022, and its expected the turbine will be operational by early 2023.
Putting it together involves the installation of the turbine and a small battery storage system, a six-kilometre access road, and a distribution line connecting it to existing lines near Inuvik's Mike Zubko Airport.
The wind project hasn't been without a snag.
On top of delays, the cost to build the access road, costs for cranes to move and assemble the turbine, and the cost of a battery storage system are all higher than anticipated.
The Northwest Territories Power Corporation (NTPC), which is responsible for the Wind Turbine Project via its sister company NT Energy, says it might cost about $20 million extra.
Part of the added costs are for the access road, the bid for which came in at $2.1 million more than was estimated in the original budget, according to Doug Prendergast, NTPC's manager of communications. The access road contract is about 15 per cent of the project total.
Prendergast counted inflation due to ongoing global supply chain issues caused by COVID-19-related lockdowns around the world and geopolitical factors as part of the reason for higher costs.

Health Minister Adriana LaGrange is alleging the former CEO of Alberta Health Services was unwilling and unable to implement the government's plan to break up the health authority, became "infatuated" with her internal investigation into private surgical contracts and made "incendiary and inaccurate allegations about political intrigue and impropriety" before she was fired in January.