Enbridge ordered to pay US$3 million for Line 3 groundwater leak
CTV
Minnesota regulators have ordered Enbridge to pay more than US$3 million for allegedly violating state environmental law by piercing a groundwater aquifer during construction of the Line 3 oil pipeline replacement.
The state Department of Natural Resources said Enbridge, while working near Clearbrook in January, dug too deeply into the ground and pierced an artesian aquifer, which resulted in a 24 million gallon groundwater leak.
"Enbridge's actions are a clear violation of state law, and also of the public trust," said Barb Naramore, DNR deputy commissioner. "That is why we are using all of the tools in our authority to address the situation."
Enbridge said in a statement Friday that it was reviewing the DNR's order and would work with the agency on a resolution.
"Enbridge has been working with the DNR since June to provide the required site information and approval of a corrective action plan which is currently being implemented," the Calgary, Alberta-based company said. "We share a strong desire to protect Minnesota waters and the environment and we are committed to restoration."