DMRC floated four civil tenders during lockdown
The Hindu
They are all for underground sections
In the last two months, when a lockdown was in place in the city, the Delhi Metro Rail Corporation (DMRC) floated four civil tenders for underground sections of the upcoming Phase 4 network. Despite reduced strength of workers, the DMRC said construction of the Phase IV network had achieved a few landmarks as well. “During these months, DMRC completed tunneling of 500 meters of one of the 2.8-km twin tunnels. It also completed casting of over 50% of tunnel segments in the casting yard. The first of the twin tunnels on this stretch is expected to be completed by September 2021,” a senior official said.More Related News