Dempster fibre line 'substantially' complete, says Yukon government
CBC
The Yukon government says the long-awaited new fibre optic line along the Dempster Highway is "substantially" complete, and should be operational by the end of the year.
"The line is in the ground, the connections have been made," said Yukon project manager Fred Jay at a news conference on Friday.
"We'll turn it over to Northwestel to complete their commissioning phase… to turn the line on, so to speak."
The project involved the installation of 778 kilometres of fibre optic line along the Dempster Highway, stretching from the Yukon to Inuvik, N.W.T. The federal government contributed approximately $60 million to the project, the Yukon government has previously said it contributed $5 million, and Northwestel contributed $15 million.
"The fibre line represents years of hard work, innovation and collaboration," said Nils Clarke, Yukon's minister of highways and public works. "It is a critical piece of infrastructure that will strengthen communication networks and support the long-term growth of the region."
The announcement comes after a series of telecommunications outages through the spring and summer that frustrated residents across all three territories.
Typically, damage to the existing fibre line — which connects the Yukon, northern B.C., northern Alberta and southern N.W.T. — means a switch over to more limited microwave internet.
The new fibre line means that when the existing southern line is damaged or interrupted, plan B kicks into gear.
"It's going to automatically reroute northeast over the Dempster fibre line and into Inuvik," said Northwestel president Curtis Shaw.
While the plan has been in the works for nearly 10 years, the project proposal was officially submitted to the Yukon Environmental and Socio-economic Assessment Board (YESAB) in 2019. Construction began in 2021.
Engineers and workers faced a number of technical challenges to lay the new line.
The majority of it is buried alongside the Dempster Highway, but the fibre line also spans wetlands and rivers. It passes through the traditional territories of eight different First Nations.
Before work began, the Yukon government consulted with scientists, traditional knowledge keepers and engineering consultants to mitigate environmental and cultural impacts.
Officials said the Dempster fibre line will ensure a significantly more resilient network in both the Yukon and Northwest Territories going forward.
A city councillor is suggesting the City of Calgary do an external review of how its operations and council decisions are being impacted by false information spread online and through other channels. Coun. Courtney Walcott said he plans to bring forward a motion to council, calling for its support for a review. He said he's not looking for real time fact checking but rather, a review that looks back at the role misinformation played on key issues. Walcott cited two instances in 2024 where factually incorrect information was circulated both online and at in-person meetings regarding major city projects: council's decision to upzone much of the city, and the failed redevelopment proposal for Glenmore Landing. "Looking back on previous years, looking back on major events and finding out how pervasive misinformation and bad information is out there and it's influence on all levels of the public discourse is really important," said Walcott.